Water plant running soon
By DONNA KENNY KIRWAN
January 15, 2008
PAWTUCKET -- With the
replacement of some problematic pumps, the Pawtucket Water Supply Board Board’s
new water treatment plant should be up and running by the end of this month or
shortly thereafter, according to a PWSB official.
James DeCelles, chief engineer, said that a stumbling block came up last summer
when it was discovered that three intake pumps that pull raw water from Happy
Hollow Pond were performing too noisily. Earth Tech, the company building the
plant, began a series of discussions with the Georgia-based manufacturer,
Patterson Pump Co., to have the situation rectified.
The pump manufacturer contended that the noise was harmless, but PSWB officials
were concerned that a problem called cavitation could
occur, eventually causing the pumps to malfunction.
Earth Tech and Patterson Pump officials spent several months locked in a
disagreement about whether or not the excessive noise was a design flaw.
However, DeCelles said the company finally agreed to remove one of the pumps and
ship it back to Georgia for modifications.
The pump was returned and re-installed with a larger impeller and it has been
readjusted to a slower speed. Earth Tech has tested the pump and said it looks
as though the modifications will solve the problem, DeCelles said.
Decelles said Earth Tech has completed the testing
that will determine whether the new treatment facility will be accepted as
meeting safe drinking water standards. The results are part of a report that
will go to the PWSB and the state Department of Health. Both bodies have 30
days to review and comment on the data.
If the test report is accepted, the facility should be set to become fully
operational by the end of this month or the beginning of next month, DeCelles
said.
The re-installation of the pipes at the pumping station will take longer, most
likely not before the beginning of May, said DeCelles. However, he said that as
it only takes one pump to supply water to the treatment plant, this part of the
project should not delay the opening date.
The $46.1 million treatment plant is being constructed behind the PWSB building
on Branch Street. It will replace an antiquated 70-year-old plant on Mill
Street in Cumberland.
The project was slated for completion by March 2006, but Earth Tech encountered
several problems that caused delays. In addition to the malfunctioning pumps,
tainted soil was discovered at the construction site, and the company
experienced a shortage of sheet metal.
The new facility will serve PWSB customers in Pawtucket, Central Falls and the
Valley Falls section of Cumberland.